Development & Humanitarian Infrastructure · Responsibility matrix
Who is responsible for what on an international modular infrastructure project?
Many project disputes begin at the boundary between the factory package and the local site package. A responsibility matrix should be agreed before order placement so every party understands what is supplied, designed, installed, checked and approved.
Planning guidance — final supplied configuration remains project-specific.
01
Do not use 'turnkey' without a schedule
The word turnkey can hide major differences in scope. Replace it with an itemised schedule covering design information, manufactured components, fixtures, services, freight, unloading, foundations, assembly, external utilities, testing, approvals and handover.
02
Separate design information from statutory responsibility
A manufacturer may provide structural calculations, shop drawings or foundation reactions without becoming the local engineer of record or statutory designer. State who checks the manufacturer's information against local law and site conditions.
03
Define the physical handover point
Clarify whether delivery ends at factory, export port, destination port, local depot or site. Then assign customs, taxes, inland transport, unloading, storage and damage inspection.
Comparison reference
Example international project responsibility matrix
Planning criterion
Manufacturer / supplier
Buyer / project team
Local professionals / contractors
Building package
Manufacture agreed components and issue package documents
Approve scope and commercial release
Review interfaces with local works
Engineering
Provide agreed system calculations / data where included
Provide project criteria
Local review, foundations and statutory sign-off as applicable
Freight
Pack and document to agreed handover point
Own agreed freight / customs scope
Receive, inspect, unload and store as assigned
Installation
Provide manuals / supervision if contracted
Appoint capable site team
Execute site assembly, temporary works and trade connections
Handover
Provide agreed records, warranty and spares
Accept and retain project documentation
Test / commission local works and close local approvals
The actual contract, Incoterm, local law and professional appointments control. This is an example framework only.
Continue planning
Related Development & Humanitarian Infrastructure resources
Direct comparison URLapollonzglobal.com/knowledge-centre/development-humanitarian-infrastructure/international-infrastructure-responsibility-matrix#comparison-matrix
Essential site functions work without analytics. With your permission, Apollo uses analytics to understand which products, guides and project pathways are useful. Analytics stays off until you allow it.