01Do not use 'turnkey' without a schedule
The word turnkey can hide major differences in scope. Replace it with an itemised schedule covering design information, manufactured components, fixtures, services, freight, unloading, foundations, assembly, external utilities, testing, approvals and handover.
02Separate design information from statutory responsibility
A manufacturer may provide structural calculations, shop drawings or foundation reactions without becoming the local engineer of record or statutory designer. State who checks the manufacturer's information against local law and site conditions.
03Define the physical handover point
Clarify whether delivery ends at factory, export port, destination port, local depot or site. Then assign customs, taxes, inland transport, unloading, storage and damage inspection.