RHELGAN · PROJECT RESPONSIBILITY MATRIX

Make every water-system interface somebody’s responsibility.

Water projects fail when tanks, treatment, foundations, external networks, electrical connections, commissioning and operations sit between scopes. This matrix is a starting framework for making those boundaries visible.

SUPPLYEquipment + defined documents
LOCAL WORKSCivil · services · approvals
OPERATIONSCommissioning · maintenance · water quality

Responsibility matrix

Use this as the starting allocation — then edit it for the contract.

“RHELGAN”, “project team” and “local works” are not legal responsibility assignments by themselves. The actual quotation, contract, consultant scope and destination requirements must name the responsible parties.

InterfaceTypical starting ownerControl point
Water demand / service briefProject team / clientRHELGAN can structure the intake; final demand basis must reflect the programme.
Source investigation + water analysisProject team / appointed local specialistsRequired before final source-specific treatment selection.
Storage equipment scheduleDefined supply scopeTank class, material, geometry and accessories confirmed for the project.
Storage structural designDefined per projectExact responsibility must be stated: equipment design, foundation design and local structural review are separate interfaces.
Foundation / civil worksLocal project works unless expressly includedSurvey, soil, slab / support, drainage, anchoring and site preparation need a named owner.
Water treatment processDefined supply / process scopeSource-water basis, finished-water target, process duty and performance responsibility must be explicit.
Pumps + controlsDefined supply scopePump duty, motors, control panel, alarms and included instruments are scheduled against the project.
External distribution networkLocal / project hydraulic design unless expressly includedPipe network, pressure zones, public mains and building connections require local coordination.
Electrical supply + earthingLocal electrical works unless expressly includedVoltage, phase, protection, earthing and connection point must match the destination.
InstallationDefined in project scheduleLocal installer, supervision, specialist assembly or commissioning roles must be named before order.
CommissioningDefined in project scheduleFunctional testing, treatment startup, water-quality verification and records need clear ownership.
Statutory / public-health approvalsResponsible local project organisations / professionalsDestination requirements remain project-specific and cannot be assumed by generic product documentation.
Operations + water-quality monitoringEnd operator / responsible organisationSampling, treatment consumables, alarms, maintenance and response procedures require an operating owner.
Warranty + sparesDefined supply scopeCovered equipment, warranty conditions, exclusions, spare-parts package and service route are documented at order.

Four boundaries to close early

These are the interfaces most likely to create gaps.

01

Tank ↔ foundation

Tank reactions, geometry, support condition, slab / plinth design, anchoring and site drainage need coordinated drawings.

02

Treatment ↔ source water

The process basis must match representative source-water data and the agreed finished-water requirement.

03

Pump ↔ network

The selected duty point depends on the external distribution system, levels, losses and peak demand.

04

Supply ↔ local operation

Spares, consumables, training, water-quality checks and maintenance responsibility must survive beyond project handover.

RHELGAN · PROJECT SCOPE CONTROL

Put the agreed responsibility matrix beside the technical schedule.

Specification Template Evidence & Documentation
Project